Operation must strictly comply with safety regulations for grounding test transformer casing and control console
Due to high voltage, operation must strictly comply with safety regulations: Grounding: The test transformer casing, control console, and non-energized end of the test object must be reliably grounded. Fencing and warning: The test area should be fenced, with a "High Voltage Danger" warning sign posted, and attended by dedicated personnel. Discharge: After the test, the test object and the high-voltage end of the transformer must be fully discharged using a discharge rod before disconnecting wires. Voltage rise speed: The voltage rise should be uniform and slow; impact closing or rapid voltage rise is strictly prohibited. If you need to select a test transformer, you usually need to pay attention to the following parameters: Rated output voltage (kV): It should be higher than the test voltage standard of the test object. Rated output capacity (kVA): It should meet the capacitive current requirements of the test object (